Research reportGPU financing

Neocloud economics: contract first, hardware second

Filings show GPU cloud operators sign customers before buying hardware, then borrow against those contracts at interest rates set by the customer's credit.

Cover of the full report: Neocloud economics: contract first, hardware second
The research behind this article, with every source listed. 17 pages.

Key points

From the Summary of the full report

  1. The GPU cloud operators studied sign multi-year take-or-pay contracts before they order hardware. Committed contracts produced over 98% of CoreWeave's 2025 revenue [1], and Nscale typically issues purchase orders once a committed contract is signed [14].
  2. Customers prepay part of each contract. Weighted averages were 15% to 25% of contract value at CoreWeave [1] and 23% at Nscale [14]. Deals signed in 2026 at Nebius and IREN carried prepayments covering 45% to 60% of the related capital spending [13, 16].
  3. Debt is secured by the hardware and the contract, repaid from the contract and priced on the customer's credit. Within the same borrower and year, the stronger credit cost two to three percentage points less: SOFR + 2.25% on CoreWeave's A3-rated facility against SOFR + 4.50% on one backed by two non-investment-grade customers [7, 8], and 6.0% against 9.0% at IREN [16].
  4. Operators report contract paybacks between one year and ten months and about 2.5 years, each on its own definition [2, 13, 16].

GPU cloud operators that build at scale work in a fixed order. They sign a customer to a multi-year take-or-pay contract, collect part of its value up front and borrow against the rest. The hardware is ordered after that. The filings of the public operators describe this order in their own words, and the terms of their debt show how much the customer's credit decides.

This article reads the filings and financing announcements of CoreWeave, Nebius, Nscale, IREN and Lambda from July 2023 to October 2026, along with the credit support NVIDIA now gives some operators.

Contracts come before purchase orders

CoreWeave says it finances its infrastructure primarily through asset-level debt supported by take-or-pay customer contracts [1]. Committed contracts produced over 98% of its 2025 revenue and had a weighted-average duration of about five years [1]. Nscale's registration statement describes "building against contracted customer demand" and says it typically issues purchase orders once a committed contract is signed [14].

Nebius tied its Microsoft agreement to its financing. The parties' obligations were to begin only once Nebius confirmed it had secured the financing for the capital spending, which it expected to raise partly as debt secured against the agreement [12].

Revenue starts later again. Nscale's contract terms begin when the GPU clusters are delivered [14]. IREN says revenue ramps after commissioning, testing and customer acceptance [16].

Prepayment carries part of the build

Customers pay part of the contract before service starts. CoreWeave's weighted-average prepayment across active contracts was 15% to 25% of total contract value at the end of 2025 [1]. Nscale reported 23% as of 31 August 2026 [14].

The share rose in 2026. About 70% of the deals Nebius closed in the second quarter included prepayments, covering 50% to 60% of the related capital spending [13]. IREN reports recent prepayments of 45% to 55% of GPU capital spending [16], against 20% of contract value on its November 2025 Microsoft contract [15].

The customer sets the interest rate

CoreWeave's 2024 facility priced each loan by the credit of the contract behind it: 6.00% to 6.50% over SOFR for investment-grade customers and 13.00% over SOFR for the rest [2]. Facilities signed since then follow the same line, and two borrowers show the split inside a single year.

Facility Closed Credit behind it Pricing
CoreWeave DDTL 4.0 Mar 2026 One customer contract; facility rated A3 SOFR + 2.25%, or about 5.9% fixed
CoreWeave DDTL 5.0 May 2026 Two non-investment-grade customers; rated Ba2 SOFR + 4.50%
Nebius secured facility Jul 2026 Investment-grade customer SOFR + 2.50%
Nscale GPU facilities Aug 2026 Facilities rated investment grade SOFR + 2.375%
Lambda term loan B Aug 2026 Investment-grade offtaker; rated Baa2 SOFR + 3.00%
IREN GPU financing Reported Aug 2026 Investment-grade customer 6.0% average
IREN GPU financing Reported Aug 2026 Non-investment-grade customers 9.0% fixed

Sources: [6, 7, 8, 13, 14, 16, 17].

For scale, overnight SOFR was 3.87% on 8 October 2026 [26]. Within one borrower and one year, the credit split is worth two to three percentage points a year, on debt that can fund 90% of the GPU spending [16]. In a SemiAnalysis model, raising a neocloud's all-in debt cost from 5.62% to 10% cut pre-tax margin from 14.8% to 5.4% [20].

Lenders also tie repayment to the contract. CoreWeave's earlier facilities must be paid down to a level based on projected contracted cash flows or on the depreciated purchase price of the servers, whichever requires more [2]. Nscale's 2026 facilities mature on the date the customer makes its final scheduled payment, if that comes before the stated maturity [14].

Payback sits inside the contract

Each operator reports a payback period, and each defines it differently. CoreWeave estimated about 2.5 years, including prepayments, from contracts in effect at the end of 2024 [2]. IREN puts recent three-year contracts at about two years, measured as GPU capital spending divided by contracted revenue less direct costs [16]. Nebius reports one year and ten months for deals signed in the second quarter of 2026, down from two to three years, on a revenue basis that excludes prepayment [13].

The figures do not compare one for one. They point the same way: the contracts are priced to return the hardware's cost before they end.

Company results still show losses

Contract payback and company profit are different measures. CoreWeave's second quarter of 2026 shows the gap. Revenue was $2,575 million and adjusted EBITDA $1,510 million. Depreciation and amortization took $1,393 million, leaving an operating loss of $49 million. After net interest expense of $640 million, other income and taxes, the net loss was $626 million [3].

Nscale had $2.6 billion of active and $103.4 billion of active and contracted contract value at 31 August 2026. It reported a net loss of $1,020.1 million on revenue of $140.6 million for the first half of 2026 [14]. Large contracts sit on the books well before their revenue does.

Short contracts and list prices move with the market

Capacity outside long contracts sells at different prices. CoreWeave said in September 2026 that it had signed three-to-six-month contracts at about $40 million per megawatt of annualized revenue [10]. Nebius reported $20 million to $25 million per megawatt on its large second-quarter deals [13]. Nebius also raised its on-demand list prices from 1 October 2026, with the HGX H100 moving from $3.85 to $4.50 per GPU-hour [25]. SemiAnalysis reported in April 2026 that on-demand capacity was sold out across GPU types [22]. Prices set in those conditions describe those conditions.

Credit support where no investment-grade customer exists

Operators without such a customer have found credit elsewhere. NVIDIA agreed in September 2025 to buy CoreWeave's residual unsold capacity through April 2032 under a $6.3 billion order [11]. Its quarterly report for the period ended 26 July 2026 lists $36 billion of commitments under agreements with superintelligence (SI) clouds, with a share of the clouds' third-party revenue when certain criteria are met [21]. SharonAI disclosed a six-year agreement with NVIDIA of up to $4.88 billion under a revenue-sharing and credit-support model [19]. For data-center leases, Google backstopped $1.8 billion of Fluidstack's lease obligations at a TeraWulf campus to support project debt [24].

Letters of intent do not finance a build

Nscale says its committed contracts typically follow the conversion of a letter of intent [14]. Semafor reported in August 2026 that Microsoft had been in talks to rent capacity at Nscale's West Virginia campus and walked away during a review of its data-center portfolio [23]. Signed contracts carry delivery risk too: some Nscale customers may terminate for delays [14].

Read the full report

The full report, with each facility's terms, the payback definitions side by side and the complete source list, is available as a PDF.

The full report

Neocloud economics: contract first, hardware second

The research behind this article, with every source listed. 17 pages.

  1. Summary
  2. Background
  3. Data and method
  4. Findings
  5. Implications
  6. Limits of this analysis
  7. Sources

Sources

  1. CoreWeave, Inc. Annual Report on Form 10-K for the year ended 31 December 2025. U.S. Securities and Exchange Commission, filed 2 March 2026. https://www.sec.gov/Archives/edgar/data/1769628/000176962826000104/crwv-20251231.htm
  2. CoreWeave, Inc. Registration Statement on Form S-1. U.S. Securities and Exchange Commission, filed 3 March 2025. https://www.sec.gov/Archives/edgar/data/1769628/000119312525044231/d899798ds1.htm
  3. CoreWeave Reports Strong Second Quarter 2026 Results. CoreWeave, 11 August 2026. https://investors.coreweave.com/news/news-details/2026/CoreWeave-Reports-Strong-Second-Quarter-2026-Results/default.aspx
  4. CoreWeave, Inc. Current Report on Form 8-K (DDTL 4.0 Facility). U.S. Securities and Exchange Commission, filed 31 March 2026. https://www.sec.gov/Archives/edgar/data/1769628/000176962826000129/crwv-20260330.htm
  5. CoreWeave Closes Landmark $8.5 Billion Financing Facility (Exhibit 99.1 to Form 8-K). CoreWeave, 31 March 2026. https://www.sec.gov/Archives/edgar/data/1769628/000176962826000129/ex991.htm
  6. CoreWeave Closes $3.1 Billion Loan Facility, Expanding Access to Public Markets for GPU-Backed Financing. CoreWeave, 18 May 2026. https://investors.coreweave.com/news/news-details/2026/CoreWeave-Closes-3-1-Billion-Loan-Facility-Expanding-Access-to-Public-Markets-for-GPU-Backed-Financing/default.aspx
  7. CoreWeave Continues to Contract New Compute Capacity at Higher Prices. CoreWeave, 17 September 2026. https://investors.coreweave.com/news/news-details/2026/CoreWeave-Continues-to-Contract-New-Compute-Capacity-at-Higher-Prices/default.aspx
  8. CoreWeave, Inc. Current Report on Form 8-K (NVIDIA order form). U.S. Securities and Exchange Commission, filed 15 September 2025. https://www.sec.gov/Archives/edgar/data/1769628/000176962825000047/crwv-20250909.htm
  9. Nebius Group N.V. Report on Form 6-K, Exhibit 99.2 (subsequent events: Microsoft agreement). U.S. Securities and Exchange Commission, filed 10 September 2025. https://www.sec.gov/Archives/edgar/data/1513845/000110465925088860/tm2525580d2_ex99-2.htm
  10. Nebius Group Letter to Shareholders, Q2 2026. Nebius Group, 12 August 2026. https://assets.nebius.com/assets/4462517b-ce83-41f2-96ed-f2ac1bc06a05/SHLQ226%20(1).pdf-0
  11. Nscale Limited Registration Statement on Form S-1. U.S. Securities and Exchange Commission, filed 18 September 2026. https://www.sec.gov/Archives/edgar/data/2110365/000119312526395475/ck0002110365-20260918.htm
  12. IREN Secures $9.7bn AI Cloud Contract with Microsoft (Exhibit 99.1 to Form 8-K). IREN, 3 November 2025. https://www.sec.gov/Archives/edgar/data/1878848/000114036125040072/ef20058139_ex99-1.htm
  13. IREN Reports FY26 Results (Form 8-K). IREN, 27 August 2026. https://www.sec.gov/Archives/edgar/data/0001878848/000187884826000051/irenreportsfy26results.htm
  14. Lambda closes $926 million senior secured term loan B facility. Lambda, 27 August 2026. https://lambda.ai/blog/lambda-closes-926-million-senior-secured-term-loan-b-facility
  15. SharonAI Holdings Inc. Registration Statement on Form S-1. U.S. Securities and Exchange Commission, filed 12 August 2026. https://www.sec.gov/Archives/edgar/data/2068385/000149315226037453/forms-1.htm
  16. Nvidia GPU Debt Backstop Unleashes the AI Project Trinity: Capital, Offtake and Datacenters. SemiAnalysis, 6 July 2026. https://newsletter.semianalysis.com/p/nvidia-gpu-debt-backstop-unleashes
  17. NVIDIA Corporation Quarterly Report on Form 10-Q for the quarter ended 26 July 2026. U.S. Securities and Exchange Commission, filed 26 August 2026. https://www.sec.gov/Archives/edgar/data/1045810/000104581026000075/nvda-20260726.htm
  18. The Great GPU Shortage: Rental Capacity. SemiAnalysis, 2 April 2026. https://newsletter.semianalysis.com/p/the-great-gpu-shortage-rental-capacity
  19. Google and Microsoft were in talks for Nscale compute deal that went to Anthropic. Semafor, 28 August 2026. https://www.semafor.com/article/08/28/2026/google-and-microsoft-were-in-talks-for-nscale-compute-deal-that-went-to-anthropic
  20. TeraWulf Signs 200+ MW, 10-Year AI Hosting Agreements with Fluidstack (Exhibit 99.1 to Form 8-K). TeraWulf, 14 August 2025. https://www.sec.gov/Archives/edgar/data/1083301/000110465925078084/tm2523008d2_ex99-1.htm
  21. Nebius AI Cloud pricing. Nebius, viewed 9 October 2026. https://nebius.com/prices
  22. Secured Overnight Financing Rate, most recent observations. Federal Reserve Bank of New York Markets Data API, retrieved 9 October 2026. https://markets.newyorkfed.org/api/rates/secured/sofr/last/3.json

Notices

Rillor is not a registered investment adviser or commodity trading advisor and does not provide investment or trading advice. Research, forecasts, data and software described on this site are for research and engineering use. Nothing here is an offer or recommendation to buy or sell any security, commodity interest or digital asset. Past or simulated results do not indicate future results.

NVIDIA, AMD, Ceph, Kubernetes and related product names are trademarks of their owners and are used only to identify products. No affiliation or endorsement is implied.

Tell us what you need to finance.

Send the systems, the deployment and any signed customer contracts, and we scope the financing with you.

Discuss financing