Forward agreements for GPU systems: how they work

A forward purchase agreement fixes the grade, quantity, price and delivery month of GPU systems at signing, with physical delivery later and no exchange or clearinghouse involved.

Published by
Rillor (Rillor Corporation)
Published
Pillar
Markets

Forward agreementsrillor.com/insights/forward-agreements-for-gpu-systemsrillor.com

Summary

  • A forward purchase agreement for GPU systems is a bilateral contract: a named buyer and seller agree at signing on the grade, quantity, price, delivery month and place, and the systems are physically delivered later. An exchange-traded futures contract standardizes those terms, routes credit risk through a clearing organization and can end by offset [3].
  • U.S. law excludes sales of a commodity for deferred shipment or delivery from the definition of future delivery, and from the definition of a swap so long as a sale of a nonfinancial commodity is intended to be physically settled [1]. The CFTC treats such forwards as commercial merchandising transactions whose primary purpose is to transfer ownership, and it judges intent to deliver on the facts and circumstances of each transaction [2].
  • The grade is the core of the contract. Futures use a basis grade with differentials [3]. A GPU forward can use a reference grade with listed differences in CPU, memory, networking and certification. Cooling and power input change what a site must provide, so air-cooled and liquid-cooled builds are separate grades [12, 13, 14].
  • Assurance can run both ways: the buyer's deposit sits with an independent escrow agent [6], and the seller posts a performance bond, an instrument that brings in a surety [7]. In futures, "performance bond" is another name for margin, a different instrument with a different purpose [3].
  • Public compute contracts show how delivery obligations are written: tranches on a schedule, a grace period, a right to terminate a late tranche when no alternative is provided, and liquidated damages for late delivery [10].
  • Power has to be reserved on the same calendar. At NVIDIA's stated rack power of about 120 kW, a 1 MW block holds 8 GB200 NVL72 racks before any allowance for networking, storage or cooling equipment, while NVIDIA specifies 1.2 MW for a scalable unit of 8 such racks [15, 16].
  • Upstream, the supply chain already runs on forward commitments. NVIDIA reports lead times of more than 12 months for certain supply and $95.2 billion of outstanding purchase, supply and capacity obligations at 25 January 2026 [9].

Background

GPU systems have long lead times, and the companies that make them commit to supply well in advance. NVIDIA's annual report for the fiscal year ended 25 January 2026 says the company builds finished products and holds inventory ahead of anticipated demand, has experienced lead times of more than 12 months for certain supply, and has paid premiums, provided deposits and entered long-term supply agreements and capacity commitments to secure future supply [9]. It reports $95.2 billion of outstanding inventory purchase and long-term supply and capacity obligations at that date [9]. It also notes that publicly announced intentions by governments or companies to buy its products are often non-binding and may not result in committed volumes [9].

Buyers face the same timing problem one step down the chain. A training cluster or a GPU cloud expansion needs systems of a known configuration in a known month, and it needs power and cooling ready when they arrive. Cloud providers sell short-dated versions of this certainty. AWS's EC2 Capacity Blocks reserve GPU instances for up to six months, can be booked up to eight weeks in advance, and are priced dynamically according to supply and demand [21]. Those reservations rent capacity. A forward purchase agreement transfers ownership of hardware and can cover a longer horizon.

Data-center capacity is the second constraint. CBRE reported a primary-market vacancy rate of 1.4% in North America at the end of 2025 and again in the first half of 2026 [19, 20]. In its report on the second half of 2025, CBRE wrote that grid-power capacity for existing projects is largely booked through 2030 in most markets, and that sites offering power access within 18 to 36 months for greenfield development are highly sought after [20].

In general terms, a forward purchase agreement, also called a forward contract, is a contract "in which a buyer agrees to purchase from a seller a specified product at a specified price for delivery at a specified future time" [22]. The CFTC glossary also lists it as a cash forward sale [3]. Its definition names a specified quality and quantity of goods and a specified future date, and lets the price be agreed in advance or determined at the time of delivery [3]. The contract obligates both parties [23]. Forwards are individually negotiated between counterparties and can be arranged for almost any product [22]. They are traded over the counter on terms that are not standardized, and they can be terminated, other than by receipt of the underlying asset, only by agreement of both buyer and seller [23]. Futures contracts, by contrast, are standardized forward contracts traded on organized exchanges [23].

Forward contracting is common in many industries, including commodity merchandising [3], and U.S. commodity law has a settled vocabulary for it. This explainer uses that vocabulary to describe how a forward purchase agreement for GPU systems works, and where it differs from an exchange-traded futures contract.

Method

This is a document review. We read:

  • the definitions in the Commodity Exchange Act [1] and the CFTC and SEC rule that further defined "swap" in 2012, including its discussion of the forward contract exclusion [2];
  • the CFTC's glossary entries for forwards, futures, margin, clearing and grades [3], and the definitions of forward contracts in the Federal Reserve Board's trading activities manual [22] and the FFIEC Call Report glossary [23];
  • the Uniform Commercial Code sections on future goods and adequate assurance of performance [4, 5], a legal definition of escrow [6], and the federal statute and regulation on performance bonds in construction contracting, used here as a reference for how such bonds work [7, 8];
  • company filings that disclose supply commitments and the delivery terms of compute agreements [9, 10, 11];
  • vendor documentation for the power, cooling and rack layout of the GPU systems named in the reference grades [12, 13, 14, 15, 16, 17, 18];
  • market reports on data-center capacity [19, 20].

We mapped each element of a forward purchase agreement (grade, quantity, price, delivery, deposit, bond and capacity) to the legal or technical source that defines it. Sizing figures are arithmetic on vendor power figures: block size divided by rack or system power, rounded down to whole units. No private agreements were used.

Findings

The Commodity Exchange Act defines "commodity" broadly. Beyond the listed agricultural products, it includes "all other goods and articles," except onions and motion picture box office receipts, and "all services, rights, and interests" in which contracts for future delivery are dealt in [1]. Two exclusions matter for deferred-delivery sales:

  • The term "future delivery" does not include any sale of any cash commodity for deferred shipment or delivery [1].
  • The term "swap" does not include any sale of a nonfinancial commodity or security for deferred shipment or delivery, "so long as the transaction is intended to be physically settled" [1].

The 2012 rule explained how the CFTC reads these exclusions [2]. Its main points, as they bear on GPU systems:

Point in the 2012 rule [2] What it says
Purpose of a forward Forwards in nonfinancial commodities are commercial merchandising transactions. Their primary purpose is to transfer ownership of the commodity, and not to transfer solely its price risk.
Why the exclusion exists The futures regulatory scheme should not apply to private commercial merchandising transactions that create enforceable obligations to deliver, where delivery is deferred for commercial convenience or necessity.
Intent to deliver Intent to deliver is part of the analysis, and the CFTC applies a facts and circumstances test, assessing the transaction as a whole.
Nonfinancial commodity A commodity that can be physically delivered and that is an exempt commodity or an agricultural commodity. An exempt commodity is one that is neither excluded nor agricultural [1].
Book-outs Under the 1990 Brent Interpretation, commercial parties who later cancel delivery obligations through a subsequent, separately negotiated agreement stay within the safe harbor. Participants that regularly make or take delivery of the commodity in the ordinary course of business meet the commercial participant standard.
Index pricing A transaction intended to be physically settled that otherwise meets the exclusion, and uses an index merely to determine the price paid for the commodity delivered, may qualify for the forward exclusion.
Consistency The entire body of CFTC precedent on forwards applies to both the swap and the future delivery exclusions.

Physical GPU systems are goods that are delivered and used. Whether a given agreement falls inside the exclusion still depends on its facts: whether both parties intend delivery, whether the contract creates enforceable delivery obligations and whether its terms let a party walk away for a cash difference. Those are questions for the parties and their counsel.

2. Forward and futures compared

Feature Bilateral forward purchase agreement Exchange-traded futures contract
Definition A cash transaction in which a commercial buyer and seller agree upon delivery of a specified quality and quantity of goods at a specified future date [3] An agreement to buy or sell a commodity for future delivery at a price set at initiation, which obliges each party to perform, is used to assume or shift price risk, and may be satisfied by delivery or offset [3]
Terms Personalized: delivery time and amount as agreed between seller and buyer; price agreed in advance or set at delivery [3] Standardized by the exchange: contract grades approved as deliverable, contract size and delivery months [3]
Venue A private contract A designated contract market, a board of trade or exchange designated by the CFTC [3]
Credit risk Each party bears the risk that the other defaults [3] Contracts executed on a designated contract market are guaranteed against default by the clearing organization [3]
Collateral As agreed: deposits, escrow and bonds Margin, also called performance bond: initial and maintenance margin, with gains and losses marked to market each trading session [3]
Ending Physical delivery of the goods Delivery, offset, or cash settlement where the contract specifies it [3]
Transfer As the agreement allows Positions close by offset on the exchange [3]

A futures position can end by offset, with no delivery at all [3]. A forward purchase agreement is written for a buyer who needs the goods in a named month.

3. The grade model

Futures markets make different lots comparable with a basis grade, the standard grade of a futures contract, and differentials, the discounts or premiums allowed for grades or locations below or above it [3]. The contract grades are those the exchange has approved as deliverable [3].

GPU systems are configured products, so a forward agreement can start from a reference grade, such as an HGX B200 8-GPU system or a GB200 NVL72 rack, and list every difference from it. The fields a grade records:

Field What it records
Reference grade The base system, such as an HGX B200 8-GPU system
CPU Platform and core count
Memory System memory size
Networking NIC count, speed and fabric
Certification The certifications the build carries
Cooling Air or liquid, a separate grade
Power input AC power supplies or DC busbar, where the system offers both
Condition and warranty New, surplus, refurbished or used, and who provides the warranty
Delivery Month and place

Cooling and power input are listed because they change what the site must provide. Vendor documentation for systems with the same GPUs shows the gap:

System Cooling Size Power Per rack
NVIDIA DGX B200 [12] Air 10 rack units 14.3 kW estimated maximum 2 in a typical deployment (28.6 kW); 4 at sites designed for extreme-density air cooling (57.2 kW)
NVIDIA DGX B300 [13] Air 10 rack units 14.5 kW power consumption AC power supply version, or a version that takes 54 V DC from a rack busbar
Supermicro HGX B200, air-cooled [14] Air 10U Not stated in the release Up to 4 per rack
Supermicro HGX B200, liquid-cooled [14] Liquid 4U Not stated in the release 8 systems and 64 GPUs in a 42U or 48U rack; up to 12 systems and 96 GPUs in a 52U rack
NVIDIA DGX GB200 NVL72 rack [15] Liquid for compute trays; networking and storage air-cooled 72 GPUs in one rack Approximately 120 kW per rack One rack

An eight-GPU B200 system can need 14.3 kW of air cooling in a rack it shares with one other system, or a coolant loop in a rack it shares with seven others. A buyer who agrees a price for "an HGX B200 system" without naming the cooling grade has agreed a price for two different deliveries.

4. Deposits, escrow and bonds

One structure for a forward purchase agreement assigns each party one instrument:

Party Instrument Held by Purpose
Buyer Deposit at signing; balance at delivery An independent escrow agent, released as the agreement sets out Commits the buyer while a neutral party holds the money until the release conditions are met
Seller Performance bond Posted by the seller, backed by a surety Backs the obligation to deliver

An escrow agent is a neutral third party that holds money, property or documents until the conditions in an escrow agreement are satisfied, and releases them only on the parties' agreed instructions [6]. The arrangement is common in real estate closings and in mergers and acquisitions, where part of the price is held to secure obligations after closing [6].

A performance bond brings in a third party, a surety, to back the bonded party's obligation. U.S. federal construction contracting uses the instrument as a matter of law: before a federal construction contract of more than $100,000 is awarded, the contractor must furnish a performance bond with a surety satisfactory to the contracting officer, in an amount the officer considers adequate [7]. The Federal Acquisition Regulation applies the requirement to construction contracts exceeding $150,000, and for contracts above $35,000 and up to $150,000 has the contracting officer choose among payment protections that include an irrevocable letter of credit and a tripartite escrow agreement [8]. These rules govern federal construction. They show bonds and escrow written into law to secure obligations that run over time.

In futures, the same words name a different thing. The CFTC glossary defines margin as money or collateral deposited with a broker, a clearing member or a clearing organization, notes that it is not partial payment on a purchase and adds that it is also called performance bond [3]. Futures margin is reset as prices move. A seller's performance bond in a forward agreement secures delivery of goods.

Two Uniform Commercial Code provisions frame the period between signing and delivery. Goods that are not both existing and identified are "future" goods, and a purported present sale of future goods operates as a contract to sell [4]. GPU systems still to be built or allocated fit that description, so title passes later. And when reasonable grounds for insecurity arise about either party's performance, the other may demand adequate assurance in writing and, if commercially reasonable, suspend its own performance; failure to provide assurance within a reasonable time not exceeding thirty days is a repudiation [5].

5. Delivery terms in public contracts

The terms of hardware forward agreements are negotiated privately. Public compute contracts show how delivery obligations are written in this market.

On 8 September 2025, Nebius disclosed a commercial agreement to provide Microsoft with access to dedicated GPU infrastructure capacity, in tranches, at a new data center in Vineland, New Jersey, over a five-year term [10]. The terms it disclosed:

Term As disclosed [10]
Delivery Several tranches during 2025 and 2026
Value About $17.4 billion through 2031, subject to deployment and availability; about $19.4 billion if additional services or capacity are acquired
Late delivery If an agreed delivery date is missed after a grace period and alternative capacity cannot be provided, the customer may terminate that tranche
Damages Liquidated damages for late delivery, alongside service level commitments
Termination for cause Material breach not remedied within 60 days, or insolvency events
Financing Cash flow from the agreement to finance part of the capital expenditure

On 17 July 2026, Nebius reported that it had delivered the latest planned capacity tranche and remained on track to deliver the remaining tranches on the contracted schedule [11]. The same announcement described a $775 million senior secured facility, maturing on 31 October 2030 and priced at SOFR plus 2.50%, backed by deployed GPU infrastructure and contracted cash flows from an agreement with an investment-grade customer [11].

The contract sells capacity as a service. The delivery mechanics carry over to a hardware forward: a named date per tranche, a grace period, a remedy for lateness, a right to substitute and a termination right that applies to the late tranche alone.

6. Sizing capacity blocks

A data-center capacity agreement reserves power and space so that systems bought forward have somewhere to run. CBRE quotes wholesale colocation asking rates per kW per month, for requirements of 250 kW and above [20]. The examples here use blocks of 250 kW, 500 kW and 1 MW.

The number of systems a block holds depends on which power figure is used. Vendor documents give several:

  • NVIDIA's DGX GB rack guide states rack power consumption of approximately 120 kW, supplied by eight power shelves of 33 kW each in an N+N arrangement [15].
  • Supermicro's GB200 NVL72 datasheet lists total power of 132 kW and operating power of 125 kW to 135 kW [17].
  • Schneider Electric's reference design for GB300 NVL72 clusters supports a maximum rack density of 142 kW [18].
  • NVIDIA's DGX B200 guidance gives 14.3 kW per system [12], and its DGX B300 guide gives 14.5 kW [13].
Block GB200 NVL72 at 120 kW GB200 NVL72 at 132 kW GB300 NVL72 at 142 kW DGX B200 at 14.3 kW DGX B300 at 14.5 kW
250 kW 2 racks (240 kW) 1 rack (132 kW) 1 rack (142 kW) 17 systems (243.1 kW) 17 systems (246.5 kW)
500 kW 4 racks (480 kW) 3 racks (396 kW) 3 racks (426 kW) 34 systems (486.2 kW) 34 systems (493.0 kW)
1 MW 8 racks (960 kW) 7 racks (924 kW) 7 racks (994 kW) 69 systems (986.7 kW) 68 systems (986.0 kW)

Derived from the vendor figures above. Counts are rounded down and include no allowance for networking, storage, management equipment, coolant distribution units or headroom.

Three points follow. First, sizing at 120 kW or at 132 kW changes the count by one rack in every block size. The power figure used for sizing belongs in the agreement. Second, NVIDIA specifies a DGX SuperPOD scalable unit of 8 DGX GB200 racks at a thermal design power of 1.2 MW [16], so a 1 MW block holds less than one scalable unit as NVIDIA specifies it, and a buyer planning NVIDIA's reference design should size to the scalable unit. Third, NVIDIA's DGX B200 guidance specifies a scalable unit of up to 32 systems at 458 kW [12], which fits in a 500 kW block.

7. The capacity market

CBRE's reports describe the market a capacity agreement is signed into:

Measure Value Period
Primary-market vacancy, North America 1.4% Year-end 2025 [20] and first half of 2026 [19]
Capacity under construction 7,481 MW First half of 2026 [19]
Share of capacity under construction already preleased More than 80%, up from 74.3% a year earlier First half of 2026 [19]
Net absorption About 1,456 MW First half of 2026 [19]
Average asking rate, 250 to 500 kW requirement, primary wholesale colocation markets $196.25 per kW per month Second half of 2025 [20]

CBRE quotes its rates as asking rates for requirements of 250 kW and above at N+1 or Tier III [20]. They are asking prices, and a signed agreement can price above or below them. CBRE also reported that operators with facilities designed for superintelligence (SI), including liquid cooling and high-power-density racks, captured rent premiums over standard colocation [20].

Implications

For buyers. Write the grade in full, including cooling and power input. Name the power figure used to size the capacity block and the cooling grade the site provides. Align the capacity agreement's start with the delivery month, so that systems do not wait for power and power does not wait for systems. Check who holds the deposit and on what instructions it is released, and who issued the seller's bond.

For sellers and integrators. A forward agreement fixes a price against supply that may itself be committed months ahead [9]. The performance bond and the delivery remedies set the cost of missing a month, so the delivery schedule in the agreement should match the seller's own supply commitments.

For lenders. A forward agreement paired with a capacity agreement gives a lender a contracted delivery month, a grade and a site. Public filings show debt secured on both deployed GPUs and contracted cash flows [11]. Before delivery, the collateral is a contract right, and the escrowed deposit and the seller's bond are part of the credit picture.

For researchers. A forward price is a contract term for a named grade, month and place. Comparing it with a spot listing or a reported sale requires matching all three.

Limits of this analysis

  • This report explains contract structure. It is not legal advice. Whether a particular agreement falls within the forward exclusion depends on its facts and circumstances [2], and only U.S. federal law is discussed.
  • The public examples of delivery terms come from a compute services agreement and from supply disclosures. Terms of private hardware forward agreements are rarely published, and none are described here.
  • The construction bonding rules cited are a reference for how performance bonds work. They do not apply to GPU purchase agreements.
  • Sizing tables use vendor power figures for reference configurations. Actual draw depends on the build, the workload and the site, and the tables exclude overhead equipment.
  • CBRE figures are asking rates and market measures for primary North American markets in the periods stated.
  • The deposit, escrow and bond structure in finding 4 illustrates one way to secure performance. The terms of any agreement are negotiated between its parties.
  • Nothing in this report is investment advice or a recommendation to enter any agreement.

Sources

  1. 7 U.S. Code § 1a, Definitions (Commodity Exchange Act). Legal Information Institute, Cornell Law School, retrieved 9 October 2026. https://www.law.cornell.edu/uscode/text/7/1a
  2. Further Definition of "Swap," "Security-Based Swap," and "Security-Based Swap Agreement"; Mixed Swaps; Security-Based Swap Agreement Recordkeeping, 77 FR 48208. Commodity Futures Trading Commission and Securities and Exchange Commission, Federal Register, 13 August 2012. https://www.federalregister.gov/documents/2012/08/13/2012-18003/further-definition-of-swap-security-based-swap-and-security-based-swap-agreement-mixed-swaps
  3. CFTC Glossary. Commodity Futures Trading Commission, retrieved 9 October 2026 and viewed 8 November 2026. https://www.cftc.gov/LearnAndProtect/AdvisoriesAndArticles/CFTCGlossary/index.htm
  4. U.C.C. § 2-105, Definitions: Transferability; "Goods"; "Future" Goods; "Lot"; "Commercial Unit". Legal Information Institute, Cornell Law School, retrieved 9 October 2026. https://www.law.cornell.edu/ucc/2/2-105
  5. U.C.C. § 2-609, Right to Adequate Assurance of Performance. Legal Information Institute, Cornell Law School, retrieved 9 October 2026. https://www.law.cornell.edu/ucc/2/2-609
  6. Escrow. Wex, Legal Information Institute, Cornell Law School, last reviewed November 2025. https://www.law.cornell.edu/wex/escrow
  7. 40 U.S. Code § 3131, Bonds of contractors of public buildings or works. Legal Information Institute, Cornell Law School, retrieved 9 October 2026. https://www.law.cornell.edu/uscode/text/40/3131
  8. FAR 28.102-1, General. Acquisition.gov, U.S. General Services Administration, retrieved 9 October 2026. https://www.acquisition.gov/far/28.102-1
  9. NVIDIA Corporation, Annual Report on Form 10-K for the fiscal year ended January 25, 2026. U.S. Securities and Exchange Commission, filed 25 February 2026. https://www.sec.gov/Archives/edgar/data/1045810/000104581026000021/nvda-20260125.htm
  10. Nebius Group N.V., Report on Form 6-K. U.S. Securities and Exchange Commission, 8 September 2025. https://www.sec.gov/Archives/edgar/data/1513845/000110465925088312/tm2525580d1_6k.htm
  11. Nebius raises $775 million in first secured debt financing to accelerate global buildout, Exhibit 99.1 to Form 6-K. Nebius Group N.V., 17 July 2026. https://www.sec.gov/Archives/edgar/data/0001513845/000110465926084452/tm2620683d1_ex99-1.htm
  12. Data Center Best Practices with DGX B200. NVIDIA, retrieved 9 October 2026. https://docs.nvidia.com/dgx-pdf/nvidia-dgx-superpod-data-center-best-practices-with-dgx-b200.pdf
  13. Introduction to NVIDIA DGX B300, NVIDIA DGX B300 System User Guide. NVIDIA, retrieved 9 October 2026. https://docs.nvidia.com/dgx/dgxb300-user-guide/introduction-to-dgxb300.html
  14. Supermicro Ramps Full Production of NVIDIA Blackwell Rack-Scale Solutions with NVIDIA HGX B200. Super Micro Computer, Inc., 5 February 2025. https://www.supermicro.com/en/pressreleases/supermicro-ramps-full-nvidia-blackwell-rack-scale-solutions-nvidia-hgx-b200
  15. Hardware, NVIDIA DGX GB Rack Scale Systems User Guide. NVIDIA, last updated 17 September 2026. https://docs.nvidia.com/dgx/dgxgb200-user-guide/hardware.html
  16. NVIDIA DGX SuperPOD: Next Generation Scalable Infrastructure for AI Leadership, Reference Architecture (DGX GB200). NVIDIA, retrieved 9 October 2026. https://docs.nvidia.com/dgx-superpod/reference-architecture-scalable-infrastructure-gb200/latest/_downloads/238ab33ee345a7241fc2f15eedc2ff6c/RA11338001-DSPGB200-ReferenceArch.pdf
  17. Supermicro NVIDIA GB200 NVL72 Datasheet. Super Micro Computer, Inc., 2025. https://www.supermicro.com/datasheet/datasheet_SuperCluster_GB200_NVL72.pdf
  18. Schneider Electric Announces New Reference Designs, Featuring Integrated Power Management and Liquid Cooling Controls, Supporting NVIDIA Mission Control and NVIDIA GB300 NVL72. Schneider Electric, 18 September 2025. https://www.se.com/ww/en/about-us/newsroom/news/press-releases/schneider-electric-announces-new-reference-designs-featuring-integrated-power-management-and-liquid-cooling-controls-supporting-nvidia-mission-control-and-nvidia-gb300-nvl72-68ca8fdd5e6c6f9d3a096133/
  19. North American Data Center Demand Continues to Outpace Supply Despite Record Construction Activity. CBRE, 27 August 2026. https://www.cbre.com/press-releases/north-american-data-center-demand-continues-to-outpace-supply-despite-record-construction-activity
  20. North America Data Center Trends H2 2025. CBRE, 25 February 2026. https://www.cbre.com/insights/books/north-america-data-center-trends-h2-2025
  21. Amazon EC2 Capacity Blocks for ML. Amazon Web Services, retrieved 9 October 2026. https://aws.amazon.com/ec2/capacityblocks/
  22. Forwards, Section 4310.1, Trading and Capital-Markets Activities Manual. Board of Governors of the Federal Reserve System, February 1998, viewed 8 November 2026. https://www.federalreserve.gov/boarddocs/supmanual/trading/4000p2.pdf
  23. Glossary, Derivative Contracts, FFIEC 031 and 041 Call Report Instructions. Federal Financial Institutions Examination Council, via the Federal Deposit Insurance Corporation, December 2025, viewed 8 November 2026. https://www.fdic.gov/bank-financial-reports/ffiec-031-and-041-glossary-december-2025.pdf
Contents

About this report

Published by Rillor on 3 November 2026. Superintelligence (SI) tools assist research and drafting, and every figure cites its source. Rillor builds and secures SI systems, supplies the data they learn from and delivers the infrastructure they run on. We apply SI to financial and compute markets.

Cite as: Rillor. Forward agreements for GPU systems: how they work. 3 November 2026. https://rillor.com/insights/forward-agreements-for-gpu-systems

Work with Rillor

Send the systems or capacity you need, the quantity, and the delivery month and location. Contact us at rillor.com/contact?type=forward or contact@rillor.com. More on forward agreements: rillor.com/markets/forward-agreements

Notices

Rillor is not a registered investment adviser or commodity trading advisor and does not provide investment or trading advice. Research, forecasts, data and software described on this site are for research and engineering use. Nothing here is an offer or recommendation to buy or sell any security, commodity interest or digital asset. Past or simulated results do not indicate future results.

NVIDIA, AMD, Ceph, Kubernetes and related product names are trademarks of their owners and are used only to identify products. No affiliation or endorsement is implied.