ExplainerData-center capacity

What to check in a data-center capacity agreement

A colocation contract decides what a GPU deployment gets and when. Filed agreements show the terms to check: committed power, delivery, cooling, service credits, liability caps and exit.

Cover of the full report: What to check in a data-center capacity agreement
The research behind this article, with every source listed. 20 pages.

Key points

From the Summary of the full report

  1. Committed power is a defined quantity at a stated point. Supermicro's 2024 service order commits "Six (6) MW (measured at the supply side of the UPS for Floor 2 Data Hall)" until its second tranche, then 12 MW, and up to 9 MW to the first floor [3].
  2. In Supermicro's 2024 documents, billing waits for acceptance. The supplier may not invoice services under acceptance tests until they are accepted or deemed accepted, and the test is Level 5 commissioning by a third-party engineering firm, which simulates loss of utility services and equipment failures [2, 3].
  3. Late-delivery remedies in the filings are daily credits and a walk-away date. Core Scientific's licenses pay $20,000 a day for days 31 to 60 past the target date and $30,000 from day 61, and allow termination without penalty after 120 days [7].
  4. Service credits, the fee reductions owed after an outage, are capped: at two quarters of fees in total in a 2015 eBay and PayPal form, and at one month's base charge a month in Supermicro's order and Core Scientific's licenses [1, 3, 7].

A colocation contract decides how much power a GPU deployment gets, when it starts paying, what it recovers when power or cooling fails and what it owes if it leaves early. Agreements filed with the SEC show how those terms are written: a 2015 colocation form between eBay and PayPal, Supermicro's 2024 master agreement and 21 MW service order, a form data center lease that a Blackstone trust filed in April 2026, and deal terms that Core Scientific, Cipher and Applied Digital disclosed [1, 2, 3, 4, 5, 7, 8, 11]. This explainer reads them as research, not legal advice.

Three terms recur. Fees run for the whole term whether or not the space is used [1, 6, 11]. Service credits are capped, and in two of the agreements they are the customer's sole remedy for outages [1, 3, 7]. Liability caps leave the customer's own fees outside the cap [1, 2, 7].

What kind of colocation contract it is

The 2015 form calls itself "a space license and services agreement" that "shall not constitute a lease" [1]. Supermicro's agreement is a master agreement, and each service order signed under it forms "a separate binding agreement" [2]. The Blackstone trust's form is a lease, which the trust says "must not be relied on" as an indication of the exact terms of any lease [5].

Term follows size. Equinix's contracts generally run one to five years, then renew automatically in one-year increments [16]. Digital Realty's contracts above 1 MW run generally 5 to 10 or more years [14].

Committed power and where it is measured

For its second-floor hall, Supermicro's service order commits "Six (6) MW (measured at the supply side of the UPS for Floor 2 Data Hall) in a block redundant configuration" until the second tranche starts, then 12 MW, and the first floor adds up to 9 MW [3]. From the power distribution units onward, the customer installs the panels, whips, receptacles and aisle containment at its own cost [3]. The 2015 form caps draw on any circuit at 80% of its breakered capacity [1].

Check whether a megawatt is critical IT or gross. TeraWulf's agreements cover more than 200 MW of critical IT load, about 250 MW of gross capacity [12]. Draw also moves inside the rack: Uptime Institute estimates that GB200 NVL72 racks can climb from around 60 to 70 kW to more than 150 kW, against a maximum specification of 132 kW [26].

Delivery, acceptance and the first invoice

In the Supermicro documents, each tranche starts when the supplier tenders possession with its installations substantially complete and the acceptance tests are passed [3]. The test is Level 5 commissioning by a third-party engineering firm, which simulates loss of utility services and equipment failures [3]. The supplier may not invoice services that are subject to acceptance tests before they are accepted or deemed accepted [2].

Blackstone's form starts the lease on the later of delivery of the first phase and that phase's completion date deadline [5]. Cipher's February 2026 presentation ties rent to rack-ready completion of each construction phase [8], and the lease's first phase commenced in August 2026 [30].

Signing to start can take more than a year. Leases Digital Realty signed in the third quarter of 2026 had a weighted-average lag of 17 months to commencement [15]. Applied Digital's June 2026 release anticipated initial operations of its 210 MW lease in the first quarter of 2028 [10]. Supermicro's order caps billing in each of its first 12 months, on a table that steps from 3,000 kW to 21,000 kW [3]. The colocation pricing explainer covers how the bill is built once it starts.

Late delivery: credits and walk-away dates

The 2015 form promises "commercially reasonable efforts" to deliver by the commencement date [1]. Core Scientific's licenses pay late-delivery credits of $20,000 a day for days 31 to 60 past the target date and $30,000 a day from day 61, and let the tenant terminate without penalty after 120 days [7]. Cipher's tenant may terminate after a 120-day delivery delay with a 30-day cure period [8]. Blackstone's form makes a daily rent credit and a later termination right the tenant's "sole and exclusive remedies" for late delivery [5]. Delay can start with the customer: Core Scientific lists customer-initiated changes in design, scope or delivery sequencing among its causes [6].

Redundancy and cooling

Uptime Institute defines a Tier III data center as concurrently maintainable, where "any part can be shut down without impacting IT operation" [19]. NVIDIA's reference architecture for Vera Rubin NVL72 systems says the data center should generally meet or exceed Tier 3 design standards [24]. The Tier levels explainer covers what each level means. The 2015 form denies all power abatement if the customer has not dual-corded its equipment, and the Supermicro order excludes interruptions caused by a failure to dual-cord [1, 3].

Supermicro's order sets the target temperature by reference to ASHRAE Class A2 and caps dew point at 69.8°F [3]. In ASHRAE's 2016 white paper, A2 allows 10 to 35°C, against a recommended 18 to 27°C [22]. The 2015 form counts a temperature failure only after cold aisles exceed 82.0°F for more than 24 consecutive hours and equipment is materially and adversely affected [1]. For liquid cooling, ASHRAE's 2021 white paper names water classes from W17 to W+ and warns that future products may need cooler water [21]. CBRE reported in August 2026 that converting air-cooled facilities to liquid cooling can bring delays beyond six months [17].

Service levels, credits and their caps

The 2015 form counts a power failure when both A and B circuits are unavailable for more than ten consecutive minutes at the receptacle, and caps total abatement, its word for service credits, at two quarters of fees [1]. On its two-year initial term, that is 25% of initial-term fees at level fees (derived from [1]). Supermicro's Outage Credit is a day of the affected space's base charge, and a 24-hour loss of both power sides earns eight (derived from [3]). Credits in a month cannot exceed that month's base charge, and three interruptions in four months, or one lasting ten days, let the customer terminate [3]. Core Scientific's licenses cap the Outage Credit at the month's base license fee [7]. The Blackstone form describes credits that may exceed a month's rent, up to 250% in its example, or have no cap [5].

Equinix says its credits and cash payments have historically "not been significant" [16]. In Uptime's 2025 survey, 57% of respondents said their "most recent major outage cost more than $100,000" [28].

Fees for the whole term and liability caps

The 2015 form makes fees "payable for the entire Term regardless of whether Customer uses the Space or Services" [1]. Applied Digital's leases are take-or-pay and non-cancellable, so a termination for convenience "would require payment of the full remaining contractual value" [11]. CBRE reported in August 2026 minimum utilization levels of 60% to 85% of allocated power in U.S. take-or-pay clauses [17].

Supermicro's agreement caps each party's liability at 24 months of charges, and the cap does not apply to the customer's obligation to pay charges [2]. Core Scientific's licenses cap claims against the operator at 12 months of base license fees outside Austin [7]. Equinix says it cannot guarantee that a court would enforce contractual limits on its liability [16].

Force majeure and the grid

Core Scientific says mandatory curtailment directed by a grid operator is force majeure under its customer agreements [6]. In Texas's ERCOT region, Senate Bill 6 has the commission set a 75 MW threshold for large loads unless it finds a lower one necessary, and requires a curtailment protocol for transmission-voltage loads interconnected after 31 December 2025 [29]. Cipher's tenant may terminate after a grid power outage of more than 180 consecutive days [8].

Term, renewal and who stands behind it

Holdover costs 200% of fees in the 2015 form, and 150% for two months then 200% in Supermicro's agreement [1, 2]. The 2015 form requires renewal notice at least six months before expiry and prices renewal at the provider's then customary rate [1]. Supermicro's agreement bars transfer of the facility's operation to anyone who is not a "Qualified Datacenter Operator" [2]. Blackstone's form makes the tenant's subordination to a mortgage conditional on a non-disturbance agreement [5], and Cipher's lease names a guarantor on each side [8]. The financeable contracts explainer reads these terms from a lender's side.

A colocation contract checklist

  1. Is it a license, a service order under a master agreement or a lease?
  2. Where is committed power measured, and is it critical IT or gross?
  3. What test accepts the space, and when does billing start?
  4. What credits and walk-away rights apply if delivery is late?
  5. What redundancy, cooling class and environmental range does the contract state?
  6. What triggers a credit, what caps it, and when can the customer terminate?
  7. Are fees owed for the whole term, and does the liability cap reach them?
  8. Does force majeure include grid curtailment?
  9. What do renewal and holdover cost?
  10. Who stands behind each side?

Rillor contracts data-center capacity for GPU systems you already hold or have on order, or reserves power and space ahead of need for a named start month, so they are ready when the hardware arrives. A capacity agreement can pair with a forward purchase agreement, which the forward agreements explainer describes.

Read the full report

The full report adds the clause text behind each term, the outage credit table, a checklist tied to its sources and all 31 sources.

The full report

What to check in a data-center capacity agreement

The research behind this article, with every source listed. 20 pages.

  1. Summary
  2. Background
  3. Method
  4. Findings
  5. Implications
  6. Limits of this analysis
  7. Sources

Sources

  1. Form of Colocation Services Agreement between eBay Inc. and PayPal Holdings, Inc. (Exhibit 10.6 to Form 10, Amendment No. 2). U.S. Securities and Exchange Commission, filed 14 May 2015, viewed 8 November 2026. https://www.sec.gov/Archives/edgar/data/1633917/000119312515188285/d877527dex106.htm
  2. Master Colocation Services Agreement between Super Micro Computer, Inc. and 4701 Santa Fe, LLC (Exhibit 10.1 to Form 8-K). U.S. Securities and Exchange Commission, filed 21 June 2024, viewed 8 November 2026. https://www.sec.gov/Archives/edgar/data/1375365/000137536524000026/prime-supermicroxmcsaxco.htm
  3. Master Colocation Services Agreement Service Order MCSA-001 (Exhibit 10.2 to Form 8-K). Super Micro Computer, Inc., U.S. Securities and Exchange Commission, filed 21 June 2024, viewed 8 November 2026. https://www.sec.gov/Archives/edgar/data/1375365/000137536524000026/pdcvernon-supermicrolamb.htm
  4. Super Micro Computer, Inc., Current Report on Form 8-K (Item 1.01). U.S. Securities and Exchange Commission, filed 21 June 2024, viewed 8 November 2026. https://www.sec.gov/Archives/edgar/data/1375365/000137536524000026/smci-20240614.htm
  5. Form of Data Center Lease Agreement (Exhibit 10.4 to Form S-11/A). Blackstone Digital Infrastructure Trust Inc., U.S. Securities and Exchange Commission, filed 29 April 2026, viewed 8 November 2026. https://www.sec.gov/Archives/edgar/data/2100161/000119312526192110/d52761dex104.htm
  6. Core Scientific, Inc., Annual Report on Form 10-K for 2025. U.S. Securities and Exchange Commission, filed 2 March 2026, viewed 8 November 2026. https://www.sec.gov/Archives/edgar/data/1839341/000162828026013305/core-20251231.htm
  7. Supplemental Information regarding Core Scientific, Inc. (Exhibit 99.2 to Form 8-K). U.S. Securities and Exchange Commission, filed 21 April 2026, viewed 8 November 2026. https://www.sec.gov/Archives/edgar/data/1839341/000119312526165121/d149019dex992.htm
  8. Cipher Mining Inc. investor presentation, February 2026 (Exhibit 99.1 to Form 8-K). U.S. Securities and Exchange Commission, filed 3 February 2026, viewed 8 November 2026. https://www.sec.gov/Archives/edgar/data/1819989/000095010326001480/dp240991_ex9901.htm
  9. Applied Digital Signs 210 MW Lease at Delta Forge 2. Applied Digital Corporation (press release), 8 June 2026, viewed 8 November 2026. https://ir.applieddigital.com/news-events/press-releases/detail/154/applied-digital-signs-210-mw-lease-at-delta-forge-2
  10. Applied Digital Corp., Annual Report on Form 10-K for the year ended 31 May 2026. U.S. Securities and Exchange Commission, filed 29 July 2026, viewed 8 November 2026. https://www.sec.gov/Archives/edgar/data/1144879/000114487926000048/apld-20260531.htm
  11. TeraWulf Signs 200+ MW, 10-Year AI Hosting Agreements with Fluidstack (Exhibit 99.1 to Form 8-K). TeraWulf Inc., U.S. Securities and Exchange Commission, 14 August 2025, viewed 8 November 2026. https://www.sec.gov/Archives/edgar/data/1083301/000110465925078084/tm2523008d2_ex99-1.htm
  12. Digital Realty Trust, Inc., Annual Report on Form 10-K for 2025. U.S. Securities and Exchange Commission, filed 13 February 2026, viewed 8 November 2026. https://www.sec.gov/Archives/edgar/data/1297996/000110465926015365/dlr-20251231x10k.htm
  13. Digital Realty Financial Supplement, Third Quarter 2026 (Exhibit 99.1 to Form 8-K). U.S. Securities and Exchange Commission, filed 29 October 2026, viewed 8 November 2026. https://www.sec.gov/Archives/edgar/data/1297996/000110465926120212/dlr-ex99d1.htm
  14. Equinix, Inc., Annual Report on Form 10-K for 2025. U.S. Securities and Exchange Commission, filed 11 February 2026, viewed 8 November 2026. https://www.sec.gov/Archives/edgar/data/1101239/000110123926000032/eqix-20251231.htm
  15. North America Data Center Trends H1 2026. CBRE, 27 August 2026, viewed 8 November 2026. https://www.cbre.com/insights/books/north-america-data-center-trends-h1-2026
  16. Tier Classification System. Uptime Institute, undated, viewed 8 November 2026. https://uptimeinstitute.com/tiers
  17. Emergence and Expansion of Liquid Cooling in Mainstream Data Centers. ASHRAE Technical Committee 9.9 (white paper), 2021, viewed 8 November 2026. https://www.ashrae.org/file%20library/technical%20resources/bookstore/emergence-and-expansion-of-liquid-cooling-in-mainstream-data-centers_wp.pdf
  18. ASHRAE TC9.9 Data Center Power Equipment Thermal Guidelines and Best Practices. ASHRAE Technical Committee 9.9 (white paper), revised 22 June 2016, viewed 8 November 2026. https://www.ashrae.org/file%20library/technical%20resources/bookstore/ashrae_tc0909_power_white_paper_22_june_2016_revised.pdf
  19. NVIDIA DGX SuperPOD: Next Generation Scalable Infrastructure for AI Factories, Reference Architecture Featuring NVIDIA DGX Vera Rubin NVL72 Systems. NVIDIA, undated (PDF created 15 September 2026), viewed 8 November 2026. https://docs.nvidia.com/dgx-superpod-reference-architecture-with-dgx-vera-rubin-nvl72.pdf
  20. Electrical considerations with large AI compute. Daniel Bizo, Uptime Institute Journal, 19 November 2025, viewed 8 November 2026. https://journal.uptimeinstitute.com/electrical-considerations-with-large-ai-compute/
  21. Uptime Announces Annual Outage Analysis Report 2026 (press release). Uptime Institute, 13 May 2026, viewed 8 November 2026. https://uptimeinstitute.com/about-ui/press-releases/uptime-announces-annual-outage-analysis-report-2026
  22. Senate Bill 6, 89th Legislature, Regular Session (enrolled version). Texas Legislature Online, 2025, viewed 8 November 2026. https://capitol.texas.gov/tlodocs/89R/billtext/html/SB00006F.htm
  23. Cipher Digital Inc., Quarterly Report on Form 10-Q for the quarter ended 30 September 2026. U.S. Securities and Exchange Commission, filed 2 November 2026, viewed 13 November 2026. https://www.sec.gov/Archives/edgar/data/1819989/000181998926000050/cifr-20260930.htm

Notices

Rillor is not a registered investment adviser or commodity trading advisor and does not provide investment or trading advice. Research, forecasts, data and software described on this site are for research and engineering use. Nothing here is an offer or recommendation to buy or sell any security, commodity interest or digital asset. Past or simulated results do not indicate future results.

NVIDIA, AMD, Ceph, Kubernetes and related product names are trademarks of their owners and are used only to identify products. No affiliation or endorsement is implied.

Reserve power before the hardware arrives.

Send the GPU systems you plan to run, the block size and cooling you need, and the month you need power.

Discuss capacity